Work continues on an Environmental Services project to replace and repair 4,508 feet of aging sewer pipe. The work includes constructing 22 green street planters and planting trees to absorb rain and reduce stormwater runoff. The project will keep about 1.6 million gallons of stormwater out of sewers annually, increase sewer system capacity and reduce basement backups.