Piedmont Sewer Repair Project Update: April 13, 2016

2016-04-14 19:40:29| PortlandOnline

Construction hours are from 7:00 a.m. to 6:00 p.m. Monday through Friday. Below is the estimated construction schedule for the rest of this week and the next two weeks. Please be aware that this schedule is subject to change due to a variety of factors, including conditions underground, weather, traffic impacts, subcontractor schedules and availability of materials.

Tags: april project update repair

 

Mt. Scott-Arleta and Woodstock Sewer Repair Project: Design is underway

2016-04-12 23:07:14| PortlandOnline

Environmental Services is designing a project to repair or replace approximately 5,600 feet, or about one mile, of public sewer pipes in the Mt. Scott-Arleta and Woodstock neighborhoods. Most of the sewer pipes are over 85 years old and are deteriorating due to age. The project will protect the public and the environment by reducing the possibility of sewage releases to homes, businesses and streets.

Tags: design project repair underway

 
 

Humboldt Sewer Repair Project - Update

2016-04-07 00:44:56| PortlandOnline

Environmental Services has completed design of the Humboldt Sewer Repair Project which will replace or repair approximately 13,000 feet of public sewer pipes that are on average 90 years old and deteriorating due to age. This is the equivalent of 2.5 miles of sewer pipes. This project will improve public infrastructure, increase sewer capacity and protect public health, water quality and the environment.

Tags: project update repair sewer

 

Piedmont Sewer Repair Project Update: March 30, 2016

2016-03-31 20:33:08| PortlandOnline

Construction hours are from 7:00 a.m. to 6:00 p.m. Monday through Thursday. Some work may occur periodically on Fridays to take advantage of openings in subcontractor schedules.

Tags: march project update repair

 

Piedmont Sewer Repair Project Update: March 17, 2016

2016-03-18 00:48:22| PortlandOnline

Crews have completed sewer construction on N Missouri Avenue from N Bryant Avenue half way down the block south toward N Dekum Street. Trenches are patched with temporary asphalt. Final trench paving will be scheduled at a later date.

Tags: march project update repair

 