Lower Powell Green Street and Sewer Repair Project Update: November 9, 2016
2016-11-10 23:02:03| PortlandOnline
As part of the Tabor to River Program, Environmental Services will soon complete construction on the Lower Powell Green Street and Sewer Project. The work includes installing 22 green street planters, planting 11 trees, and repairing or replacing 4,508 feet of public sewer pipe. These improvements will extend the service life of our sewer system and protect public health, property and the environment by reducing the possibility of sewage releases into streets, homes and businesses.
Tags: november
street
project
lower
Piedmont Sewer Repair Project Update: November 4, 2016
2016-11-08 00:53:13| PortlandOnline
Night work on North Lombard Street between North Kerby and Vancouver avenues is scheduled to begin next Monday, November 7, through Friday, November 18
Tags: november
project
update
repair
RecoverNW23 Project Update 1- Nov. 4, 2016
2016-11-05 01:20:38| PortlandOnline
PDF Document, 285kbCategory: Recovery Newsroom
Tags: project
nov
update
update project
Hollywood/Grant Park Sewer Repair Project Update
2016-11-04 23:24:22| PortlandOnline
Currently our contractor is finishing up the night work on NE Halsey. The night pipe work is expected to last through the week of November 14. Final trench paving will take place at a later date once temperatures and dry weather allow this phase of the work to be completed.
Tags: project
park
update
repair
Powell Sewer Repair Project Update
2016-11-03 20:27:01| PortlandOnline
The maps posted at www.portlandoregon.gov/bes/powell show the anticipated construction schedule through February 2017 and a look ahead through November 18. Work in each area will take a few weeks to complete and there will be periods of inactivity between construction phases.
Tags: project
update