je.st
news
Tag: update construction
SE 20th and Haig Sewer Construction Update: March 25, 2015
2015-03-26 00:52:17| PortlandOnline
Environmental Services has started construction on a project to replace aging sewer pipes on SE 20th Avenue from SE Lafayette to Haig streets, and on SE Haig Street from SE 20th to 18th avenues. The pipes are over 100 years old and in poor condition. The project will protect the public and the environment by reducing the possibility of costly breaks, leaks, blockages and sewage releases to homes, businesses and streets.
Tags: march
update
construction
20th
Clinton Green Street and Sewer Construction Update: March 17, 2015
2015-03-18 16:18:43| PortlandOnline
As part of the Tabor to the River Program, Environmental Services continues construction on the Clinton Green Street and Sewer Project. This project will replace 3,800 feet of sewer pipe installed over 100 years ago, construct 24 green street planters and add two blocks of pervious paving. These improvements will protect public health, property and the environment, and reduce the possibility of sewage releases into streets, homes and businesses.
Tags: march
street
update
green
SE 20th and Haig Sewer Construction Update: March 10, 2015
2015-03-12 00:32:37| PortlandOnline
Construction has begun on an Environmental Services project to replace aging sewer pipes on SE 20th Avenue from SE Lafayette to Haig streets, and on SE Haig Street from SE 20th to 18th avenues. The pipes are over 100 years old and in poor condition. The project will protect the public and the environment by reducing the possibility of costly breaks, leaks, blockages and sewage releases to homes, businesses and streets.
Tags: march
update
construction
20th
Clinton Green Street and Sewer Construction Update: March 9, 2015
2015-03-10 23:47:52| PortlandOnline
As part of the Tabor to the River Program, Environmental Services continues construction on the Clinton Green Street and Sewer Project. This project will replace 3,800 feet of sewer pipe installed over 100 years ago, construct 24 green street planters and add two blocks of pervious paving. These improvements will protect public health, property and the environment, and reduce the possibility of sewage releases into streets, homes and businesses.
Tags: march
street
update
green
Eastmoreland-Woodstock Sewer Repair Project Construction Update: March 3, 2015
2015-03-04 18:19:19| PortlandOnline
Construction is winding down on this project to repair or replace about 40,000 feet of severely deteriorated sewer pipes that are more than 60 years old. The work will make the sewer system work more effectively and protect water quality, public health and the environment.
Tags: march
project
update
construction
Sites : [4] [5] [6] [7] [8] [9] [10] [11] [12] [13] [14] [15] [16] [17] [18] [19] [20] [21] [22] [23] next »