je.st
news
Tag: update construction
Clinton Green Street and Sewer Construction Update: August 29, 2014
2014-09-02 17:50:00| PortlandOnline
As part of the Tabor to the River Program, Environmental Services will begin construction on the Clinton Green Street and Sewer Project next week. Over the next year, this project will replace 3,800 feet of sewer pipe installed over 100 years ago, construct 24 green street planters and add two blocks of pervious paving. These improvements will protect public health, property and the environment, and reduce the possibility of sewage releases into streets, homes and businesses.
Tags: august
street
update
green
Vernon-Sabin-Alameda South Construction Update: August 21, 2014
2014-08-22 00:00:20| PortlandOnline
Environmental Services is replacing 10,030 feet of public sewer pipes that are between 92 and 104 years old and in poor condition. This project will help protect the public and the environment by reducing the possibility of costly breaks, leaks, blockages and sewage releases to homes, businesses and streets.
Tags: august
south
update
construction
Eastmoreland-Woodstock Sewer Repair Project Construction Update: August 21, 2014
2014-08-21 23:41:47| PortlandOnline
Construction continues on a project in your neighborhood to repair or replace about 40,000 feet of severely deteriorated sewer pipes that are more than 60 years old. The work will make the sewer system work more effectively and protect water quality, public health and the environment.
Tags: august
project
update
construction
Clinton Green Street and Sewer Construction Update: August 18, 2014
2014-08-19 23:20:19| PortlandOnline
As part of the Tabor to the River Program, Environmental Services will begin construction on the Clinton Green Street and Sewer Project next week. Over the next year, this project will replace 3,800 feet of sewer pipe installed over 100 years ago, construct 24 green street planters and add two blocks of pervious paving. These improvements will protect public health, property and the environment, and reduce the possibility of sewage releases into streets, homes and businesses.
Tags: august
street
update
green
Construction Update
2014-07-12 00:01:16| PortlandOnline
Tags: update
construction
construction update
update construction
Sites : [13] [14] [15] [16] [17] [18] [19] [20] [21] [22] [23] [24] [25] [26] [27] [28] [29] [30] [31] [32] next »